Rebuilt Vacuum Furnaces

Graphite Furnace Systems Has a Complete Rebuilding Facility.

We will develop a project scope which includes as little as a controls upgrade to complete system rebuild with a new chamber, hot zone, controls, plumbing, wiring and rebuilt pumps.  We perform a rebuilding project with the same philosophy as a new custom furnace project keeping quality and customer satisfaction as our utmost goal.

GCA / VI Sintervac

500 1600° C Sintering Furnace

Scope of the Rebuild:

  • Used existing heater transformer
  • Used existing power feed throughs
  •  Rebuilt existing pumps
  •  Reskinned the outer vessel.  Interior jacket was Stainless Steel
  • Relined hot zone
  • New elements
  • New gas plumbing
  • New water plumbing
  • New controls and wiring
  • New external forced cooling system consisting of a water cooled cooling fan and external heat exchanger with isolation valves

BEFORE

AFTER

Custom designed furnaces …